08/05/2026
Today Milestone Contractors will begin roadway improvements on County Road 450S from Old Lane Drive to 50W as part of the Community Crossings Matching Grant Program. The project will utilize cold in place asphalt recycling, an environmentally friendly and cost efficient pavement rehabilitation method that reduces waste and lowers material usage.
Work Schedule:
• This Wednesday–Friday: Crews will mill the existing pavement along the project limits.
• Monday, August 10 – Friday August 14: Application of the recycling treatment is scheduled.
• Afterward, crews will allow the roadway’s moisture content to reach acceptable levels before placing the final asphalt prior to Friday, August 28.
Drivers should expect periodic delays, flagging operations, and reduced speeds throughout the work zone. Motorists are urged to use caution and avoid the area when possible. These improvements are part of the City’s ongoing commitment to maintaining safe, durable, and sustainable roadway infrastructure.