** BRUXNER HIGHWAY ROUNDABOUT PROGRESS AND TRAFFIC CHANGES **
Work continues to progress on the Bruxner Highway/Patricia Street roundabout, with transition to stage 3 works scheduled to commence from Monday 16th November 2026.
Stage 3 will include:
o Asphalt surfacing
o Construction of splitter islands and completion of the central roundabout island
o Kerb, gutter and drainage work
o Installation of remaining streetlights and underground wiring
o Road signage and final line marking
o Batter trimming, topsoiling, and seeding
Changing Traffic Conditions
Motorists are advised that traffic conditions will change as works progress through Stage 3. Traffic control, barriers and signage will be in place, and motorists are asked to follow all directions and allow additional travel time.
Monday 16th and Tuesday 17th November
o Traffic will remain on the southern side of the roundabout during construction hours, with one-lane alternating traffic flow.
o Two lanes will reopen outside construction hours.
o From Wednesday 18th November for approximately 3 weeks
During construction hours, traffic will be diverted to the northern side of the roundabout, with one-lane alternating traffic flow.
o Outside construction hours, two lanes will be open, using the outer lanes on the northern and southern sides of the roundabout.
o Works may also occur on Saturdays where required.
Stage 3 works are expected to take approximately three weeks, weather permitting, with the overall project remaining on schedule for completion by the end of December 2026.
Council thanks motorists and the community for their patience while these works are completed.