14/10/2026
🚧 Works Update - 14 October 2026 🚧
Work on Stage 1 of the $2.5 million Civic Heart Project began last week. Stage 1 delivers the heart of the project by transforming the space between the Library and Council Chambers into a welcoming civic plaza where community can gather. The works include pedestrian pathways and forecourts, landscaping, seating, accessibility upgrades and supporting infrastructure.
The Clarkes Lane/Saville Street project continues to progress, with the bridge now complete and all handrails installed on both the bridge and approach sections. The shared path on the Clarkes Lane side has been completed to the Newpark vehicle entrance and crews continue upgrading stormwater drainage to accommodate the next section of footpath connecting to the Summerland Way path at the Newpark pedestrian entrance. Construction of the footpath on the Daleys Lane side of the bridge is also progressing.
Work commenced this week on an upgrade of Clarence Way near Hootens Road. The project involves a 1.4 km section of pavement strengthening, widening and overlay, expected to continue through to March 2027. The project is being delivered with support from The Safer Local Roads Infrastructure Program (SLRIP) - an Australian Government funding scheme helping to improve safety, resilience and driving conditions.
Grading works are continuing throughout the Cawongla catchment, which remains a significant work area with a large number of roads affected by damage. Crews are also back in Collins Creek undertaking pothole repairs and grading works as part of the ongoing maintenance program.
On the Bruxner Highway project, crews returned to site this week to complete steel fixing for the base slabs on both sides of the culvert extension, with preparations also progressing for the upcoming concrete works.
Flood damage works wrap up:
🔹 Iron Pot Creek Road: Council continues to monitor the landslip
🔹 Baileys Bridge Road: Completed
🔹 Gradys Creek Road landslip: Rock treatment wall and piling platform completed. Piling to commence this month.
🔹 Richmond River/Bowling Club Slip: Slip 1 and 2 completed, final slip completed this week
🔹 Williams Road landslip: Soil nailing in progress
Meanwhile, reconstruction works on Gardener Lane are continuing, with crews currently backfilling driveways to restore property access and undertaking general site clean-up activities.
A new round of water main renewal works is also set to commence this week in Rous Street, Mount Street, Fairy Street, Earl Street and Roseberry Street. To date, 1.25 kms of ageing cast iron water mains have been replaced, and completion of these streets will bring the total renewed to 2.5 kms, representing a quarter of Council's 10 km renewal target.
Image: Richmond River/Bowling Club Slip