23/08/2026
๐ง MAJOR A38 Egginton/Willington Bridge works (Near New McDonalds) โ information events in Repton
I know there has been quite a bit of concern locally about the upcoming works on Egginton/Willington Bridge, particularly the potential impact on traffic through Willington/Repton and surrounding villages.
Major improvement works on the A38 are planned to begin on Monday 21 September 2026 and are expected to continue until summer 2028.
Highways aim to keep the A38 open as much as possible throughout the scheme to reduce disruption, but some traffic management measures and overnight closures will be required.
๐ฃ๏ธ A38 traffic management
๐
21 September 2026 โ 26 August 2027
โข A38 open 24/7 with two narrow lanes in each direction
โข 40mph speed limit in place between A5121 (Claymills) and Toyota Interchange
๐
27 August 2027 โ 6 June 2028
โข A38 open 24/7 with one lane in each direction
โข 40mph speed limit in place between A5121 (Claymills) and Toyota Interchange
โ ๏ธ Overnight closures required
To allow for traffic management installation, bridge propping and excavation works, the A38 will need to close overnight between Toyota Interchange and A5121 (Claymills) on selected weeknights, from 8pm to 6am:
๐น 21โ22 September 2026 โ A38 northbound closed
๐น 22โ25 September 2026 โ A38 southbound closed
๐น 28 Septemberโ2 October 2026 โ A38 northbound closed
๐น 21โ27 October 2026 โ A38 northbound closed
๐น 16โ17 November 2026 โ A38 northbound closed
๐น 14โ18 December 2026 โ A38 southbound closed
๐น 4โ8 January 2027 โ A38 southbound closed
๐น 21 Januaryโ3 February 2027 โ A38 northbound closed
โ ๏ธ A5132 Carriers Road Bridge
๐
21 September โ 9 October 2026
There will be two-way traffic lights in operation on the bridge.
๐
9 November 2026 โ 3 June 2027
The bridge will be fully closed to vehicles while works take place.
๐ถโโ๏ธ๐ดโโ๏ธ๐ Pedestrians, cyclists and horse riders will still be able to cross the bridge during the full closure.
Iโve been working with the Highways and National Highways teams to make sure residents are properly informed, and Iโm pleased they have agreed to hold two public information events at Repton Village Hall.
๐
Tuesday 8 September โ 9.30am to 12.30pm
๐
Thursday 10 September โ 4.00pm to 8.00pm
This is a good opportunity to see the plans, understand the proposed traffic management and diversion routes, and most importantly ask the project team your questions directly.
I appreciate these works are likely to cause some disruption, so the more information we have beforehand, the better prepared we can be.
If you regularly use the A38, have children travelling that way to school, or run a local business, Iโd encourage you to pop along.
You can also sign up for weekly traffic updates by emailing [email protected].
Iโll be keeping a close eye on the works and their impact on Willington/Repton and the surrounding villages.