United Utilities works : West Vale, Beeston & St Leonards
Many residents have complained about the longstanding and delayed UU works on West Vale, Beeston and St Leonards.
Yesterday I met on site with the project manager Pam. She has explained that there have been three delays, and apologises for having to again extended the works permit.
1) The job was initially intended to be “slip replacement” where new plastic pipes are fed/slipped inside old iron pipes. Unfortunately the old pipes were in such a poor condition that this wasn’t possible to achieve. This greatly increased the scope of work and time.
2) The crew they had were called away to an emergency burst near Chester (which is now repaired)
3) A new crew is back and now working at pace, but they are currently delayed as the valve (photo attached) is so badly deteriorated that it needs an emergency replacement (or they need to temporarily cut more people off, which the site manager is keen to avoid)
The upshot of these delays is that the site manager knows she will not be able to complete West Vale by the 10th July (her current permit limit) and that she will have to extended this, now for the fourth time. They do expect to complete Beeston by its permit date of 30th July.
An added advantage of walking the site with UU was they accepted a number of spot fixes (including destroyed pavements and defects). I have also raised the "undermining" of the trees/roots.
I have direct communications with the management team on this job now, and have told them I will be passing your concerns/issues on. So, if you have any problems or questions, please just ask, it will reach them.