31/10/2026
Today: Roof installation begins, Wickham training plus Tinkabells….
Good conditions on site for late autumn, with mild temperatures, some afternoon sunshine, no rain and, most importantly, no wind. Although the workforce was slightly reduced, there were sufficient volunteers present to make good progress on the priority tasks.
With the refurbishment of the Wickham trolley and Dough wagon now complete, and wagon B10 in the final stages of rebuilding, attention has begun to turn towards the extensive programme of Winter 2026 projects. Before work commenced, there was an opportunity for some driver familiarisation training with the Wickham trolley in the main yard.
Work continued on the restoration of Ruston Tinkabell, this time with the removal of old paint from the rear buffer beam and main frames. Later in the day, the rear buffer beam received a fresh coat of paint, marking another visible step forward in the locomotive's refurbishment.
Refurbishment work also continued on Hunslet No. 15 ahead of the installation of the new brake actuator cylinder. Although the cylinder has now been delivered, adaptor unions are required due to differences between the thread arrangements on the new unit and the existing pipework. During the afternoon, the alternator was removed for further investigation after problems were identified with the adjustment mechanism, resulting in inadequate charging.
A significant milestone was reached with the commencement of roof renewal works on Shed 83D. The existing tarpaulin covering was removed from one structural bay, and the scaffold tower was extended to provide access. The panels were then lifted externally and slid into position on the purlins, where they were secured using rivets and brackets from the safety of the scaffold tower. The method proved effective and allowed all fixing operations to be completed safely from the platform. By the end of the afternoon, three roof panels had been successfully installed. Given that the team was developing and refining the installation sequence as work progressed, this represented excellent progress for the first day of the project.
Overall, it was a productive day across a number of work fronts, with tangible progress made on locomotive restoration, infrastructure improvements and a start on the winter programme of works.