Why can’t construction start at every location at the same time?
Before construction can begin at a transmission-line location, various processes may need to be completed, including:
▪️ Ownership and documentation verification
▪️ Valuation and compensation
▪️ Easement registration
▪️ Succession processes
▪️ Access arrangements
▪️ Resolution of ownership and other legal matters
Kenya Electricity Transmission Company Limited (KETRACO) continues to engage affected landowners and relevant stakeholders to address outstanding matters and facilitate construction.
Follow the Narok–Bomet journey as KETRACO continues to expand Kenya's transmission network.