10/15/2026
Charleston's Working Waterfront Is One Step Closer to a $2.3 Million Investment!
Tomorrow, October 16, is the final day to submit public comment in support of the Charleston Shipyard Revitalization Project.
At today's Port Commission meeting, Charleston Marina and Shipyard Manager Ray Dwire provided an update on the project, which has been recommended for $2.3 million in funding through ODOT's Connect Oregon program.
Ray's presentation also highlighted another recently failed component of the shipyard's aging marine ways system, creating an additional need for funding to make short-term repairs. It's another reminder of why this investment is so important. Rather than continuing to invest in temporary fixes to aging infrastructure, the Charleston Shipyard Revitalization Project offers a long-term solution.
Ranked 9th out of 35 applications statewide, the project is in a strong position to receive funding (the top 12 projects are recommended for funding, the funding list is below). Historically, the Oregon Transportation Commission has approved ODOT's final funding recommendations, but the decision is not yet official. Continued public support helps reinforce the importance of this investment to Charleston and the broader South Coast.
The Charleston Shipyard is the only public shipyard on Oregon's South Coast and a vital part of our working waterfront. This $3.3 million project would replace the aging marine ways system used to haul vessels out of the water for repairs and maintenance, helping restore shipyard capacity, support our commercial fishing fleet, and keep maritime jobs and economic activity in our region.
With $1 million in federal funding already secured through the support of Congresswoman Val Hoyle, the requested Connect Oregon funding would complete the funding needed for Phase 1 of the revitalization effort.
There's still time to make your voice heard!
Public comments are open through Friday, October 16, ahead of the Oregon Transportation Commission's final funding decision expected in December.
We appreciate the community members and organizations who have already submitted letters of support. If you'd like to add your voice, comments can be emailed to [email protected] by close of business October 16.
View the Final Review Committee's Prioritized Funding Recommendations:
https://www.oregon.gov/odot/Programs/TDD%20Documents/FRC_Final.pdf
Learn more about the project and its importance to Charleston's working waterfront:
https://www.portofcoosbay.com/questions-answers-charleston-shipyard-revitalization-project