10/02/2026
SCC Announces: School Project Crews to Work Added Saturday Shifts to Keep Projects on Schedule for Fall 2027 Opening
Hanaford Elementary School
Saturday, October 3, 2026 | 7:00 AM – 3:00 PM
Consigli Construction – Site supervision.
Empire – 4–6 workers on site to receive a delivery and erect staging. Crews continuing exterior masonry brick finish, roofing, and weather-tight application work.
East Greenwich High School
Saturday, October 3, 2026 | 7:00 AM – 3:00 PM
Consigli Construction – Site supervision.
Peregrine Mechanical – Boiler startup.
Energy Electric
Standby support for boiler startup.
Continuing overhead rough-in work in the locker room and upper gym.
Spino – Finish concrete and masonry work in the locker room; installation of lintels at exterior window openings.
Most work has transitioned to the interior, as several impacted high school spaces are scheduled for completion and turnover for use in the coming months, with the remaining spaces ready for use by the end of the school year.
Frenchtown Elementary School
Saturday, October 3, 2026 | 7:00 AM – 3:00 PM
Consigli Construction – Site supervision.
Greenwood Roofing – Roofing crews on site.
Brunca – Installation of air/vapor barrier (AVB).
Larkin – Ductwork installation.
DiGregorio – Exterior utilities work.
Work continues on the exterior masonry brick finish, roofing, and weather-tight applications at both elementary school sites. Crews are working to secure the buildings for the winter season, then will transition to interior work through the winter months, with anticipated completion by late Spring/early Summer 2027.