08/27/2026
Landscape Update
We're paying close attention to the new landscaping along Montrose Boulevard, and we want to thank residents and neighbors for bringing their concerns to our attention, which we've also observed and share.
Some recently planted trees between West Clay and Allen Parkway are showing the effects of Houston’s extreme summer conditions, and our landscaping team is responding. We are working closely with our contractor and arborist to assess each affected tree and determine the next best steps.
The project includes safeguards for situations like this. The trees are covered by a four-year warranty, and each one will be evaluated to determine whether it needs additional care, or replacement.
This is the process working as intended. Our shared goal is to help the landscaping thrive over the long term and ensure that Montrose Boulevard becomes greener and more beautiful as the project matures.
We expect recommendations from the contractor and arborist in the coming weeks and will continue keeping the community informed about our progress.
All updates will be posted on the Montrose Boulevard Project Page. https://montrosehtx.org/projects/montrose-blvd-improvement-project/
Matt Brollier
Chair, Montrose RDA/TIRZ 27
NOTICEThere is a City of Houston Public Works project that started on Montrose from W. Clay to Westheimer. It is not affiliated with the Montrose TIRZ. It includes resurfacing the roadway, ADA compliant sidewalk ramps and sidewalks in spot locations, and replacement and upgrade of storm sewer inlets...