10/23/2026
Green Bay Road Reconstruction Update: October 23, 2026.
This project is expected to be complete the week beginning November 9.
Saturday, October 24
Final grading of the road base will continue on Green Bay Road from West Center Avenue to West Hawthorne Court. The road will be closed one block at a time as the work progresses from north to south. Crews will be grading and cleaning up the parkways in preparation for landscaping.
Monday, October 26 – Saturday, October 31
Final grading of the road base will be completed on Green Bay Road from West Center Avenue to West Hawthorne Court in preparation for asphalt paving on Tuesday, October 27. The road will be closed one block at a time as the work progresses from north to south.
Asphalt paving will continue on Tuesday, October 27 to finish the bottom layer of asphalt on Green Bay Road from West Center Avenue to West Hawthorne Court. There will be flaggers onsite to help direct traffic through the work zone.
Utility frames will be adjusted in the road after the bottom layer of asphalt is complete.
Crews will pour concrete for open sidewalk gaps later in the week.
Asphalt driveways will begin next week after the binder is complete.
Work on Saturday, October 31 will end at 2:00 PM (ahead of Trick-or-Treating from 4:00 PM – 7:00 PM)
Please use caution when traveling through the work zone, follow all traffic control personnel and signage, and allow additional travel time.
For the latest construction updates, maps, and project information, visit lakebluff.org.