10/23/2026
At the time of recording, Harvest Water had close to $420 million in outside funding lined up for its $597 million budget.
Jofil Borja manages the administrative program management office for the project at the Sacramento Area Sewer District. Most of the money comes from the state through Proposition 1 and the California Water Commission, tied to a commitment to deliver ecological benefits to the region for 84 years.
The rest includes $30 million from the U.S. Bureau of Reclamation and a $5.5 million cost share from the Sacramento County Department of Transportation. A $1 million U.S. Department of Agriculture grant and $15 million from the State Water Resources Control Board are also lined up.
Along with 42 miles of new pipeline, the project improved close to 40 miles of rural roads in southern Sacramento County, some of which had been deteriorating for years.
Those roads carry farm traffic in a county where agriculture is roughly a half-billion-dollar industry, according to the Sacramento County Farm Bureau and the county agricultural commissioner.
“You need to be able to get their products from point A to point B.”
Construction ran as six projects at the same time over about 18 to 24 months, with a counterpart at the district overseeing the capital program management office alongside consultants and contracted construction companies. “It takes a whole village, Derek. It really does.”
At the time of recording, every impacted road had reopened. The pump station at the EchoWater facility was still under construction, along with on-farm connection assemblies that tie the new pipes into growers’ irrigation equipment.
Guest: Jofil Borja, Environmental Legislative & Regulatory Affairs | Harvest Water APMO, Sacramento Area Sewer District
Hear from government and public sector leaders, transportation executives, funding decision makers, development managers, and more who are shaping our industry.
Watch more of the Between Two Shovels show and subscribe to our Connector JPA project updates email list at connectorjpa.com/between-two-shovels
Title: How Harvest Water Was Funded and Built: $420M in State Funding, 42 Miles of Pipeline