Revised Paving Plan – Brookline Street Update 8/13/26
The Town of Pepperell has revised its 2026 paving plan. Full milling and paving of Brookline Street, from Prescott Street to Hollis Street, will no longer take place this year. The Department of Public Works will address specific areas of Brookline Street as needed in the interim. Full paving of Brookline Street, from Prescott Street to Hollis Street, is anticipated to be included in next year’s paving schedule, subject to available funding and scheduling.
All other streets included in the current Chapter 90 paving project remain scheduled as posted.
----------
Roadwork Notice: Milling and Paving Scheduled for End of August 2026
Jewett Street, Shattuck Street, Hog Hill Road, and Brookline Street
The Town will be conducting milling and paving work at the end of August, weather permitting, in the following areas:
• Jewett Street, from Route 113 to house #124
• Shattuck Street, from Jewett Street to Route 119
• Hog Hill Road, from West Street to the Townsend town line
• Brookline Street, from Prescott Street to Hollis Street
Residents should expect road closures, traffic delays, and detours during this work. Please plan ahead and avoid these areas whenever possible.
Thank you for your patience and cooperation.