09/28/2026
An FYI for you all regarding the paving that will be happening in Southwest Harbor!
2026 SWH PAVING SCHEDULE
(weather permitting)
October 12th, 2026: Complete shim paving on Clark Point RD & Herrick Rd
October 13th, 2026: Start sidewalk paving on Clark Point Rd sidewalk
October 14th, 2026: Complete sidewalk paving on Clark Point Rd sidewalk
October 15th, 2026: Surface Robinson Lane and Fernald Point Rd
October 16th, 2026: Surface Clark Point Rd and Herrick Rd
October 19th, 2026: Start driveway lips on Robinson Lane and Fernald Point Rd
October 20th, 2026: Finish driveway lips on Robinson Lane and Fernald Point Rd
October 21st, 2026: Start driveway lips on Clark Point Rd
October 22nd, 2026: Finish driveway lips on Clark Point Rd
October 23rd, 2026: Start driveway lips on Herrick Rd
October 26th, 2026: Finish driveway lips on Herrick Rd
October 27th, 2026: Miscellaneous clean-up Project Complete
MaineDOT SEAWALL PROJECT
October 5, 2026-November 13, 2026 (weather permitting)-Seawall Road closed at S-curve; paving schedule TBD within this timeframe.