09/18/2026
UPDATE: Due to weather, prep work on driveways will begin today, 9/22, on N Bonsall Road and Ruthland Ave. The remainder of the schedule will remain as listed below. Any further changes will be posted.
West Caln Township will be completing paving on the following roads within the township: Ruthland Avenue, North Bonsall Road, Reservoir Road and Zaleski Road. The planned roadwork schedule is below and is weather dependent.
- Thursday September 24th, 2026- Prep work to be completed for the 4 roads
- Friday September 25th, 2026- Paving of Ruthland Avenue and North Bonsall Road, any prep work not completed on the 24th will be done following the paving of these roads.
- Monday September 28th, 2026- Reservoir Road and Zaleski Road
Roads will be closed to through traffic during this time. Please plan accordingly and allow for extra time in your travels.