NOTICE: GREENWOOD LAKE DRAWDOWN TO COMMENCE IN THE FALL OF 2027
The water level management plan for GWL calls for an optional 5' drawdown every four years. While 2026 is a scheduled drawdown year, due to the commencement of a NJDEP capital project to repair/upgrade the Greenwood Lake Dam sluice gate mechanism, the Greenwood Lake Commission has approved rescheduling the next drawdown to commence in the Fall of 2027.
Background on this decision is as follows:
Over time, the operation of the Greenwood Lake Dam sluice gates has become increasingly difficult and more unreliable as a result of normal use and aging of mechanical components.
In 2025, the Greenwood Lake Dam was given priority for a capital repair, the initial phase of which was commenced in June 2026 by the New Jersey DEP.
The capital project will include Project Engineering & Planning, RFP Process & Contract Award, and Project Implementation & Completion.
When available, updates to the capital project schedule will be posted or made available on GWLC.org or via link to NJ DEP website.
This project is an important element of NJDEP's work to maintain the Greenwood Lake Dam infrastructure and is fully supported by the Greenwood Lake Commission. Once completed, future drawdowns can proceed again as optioned every four years.