11/03/2026
🚧 Construction on the Sunnyside Road Multi-Use Pathway Project is progressing northbound along Sunnyside Road, with the next phase of work beginning north of East Road on Monday, November 2.
Over the next couple of weeks, the existing asphalt pathway will be removed and widened in preparation for repaving.
What to expect:
🚶 Temporary pedestrian access closure along the sidewalks within the active construction area for approximately two weeks.
🚗 Single-lane alternating traffic as construction progresses northbound along Sunnyside Road.
👷 Construction activity and temporary traffic control as crews remove and widen the existing pathway.
The contractor will work to minimize disruptions wherever possible. Please follow posted signage and directions from traffic control personnel.
Construction is anticipated to continue through late November, weather permitting. Please note that all timelines are subject to change.
🔗 For more information and project updates, visit the Village’s project page: anmore.com/road-projects