A63 Castle Street – November overnight closures / work on Murdoch’s Connection
We’re planning essential overnight closures to complete the permanent electronic message signs on the A63 Castle Street.
The new signs will provide clearer, timely information about incidents, congestion, closures, and lane availability, helping drivers make safer decisions and supporting smoother journeys.
Overnight closures are planned eastbound and westbound:
• Monday 2 to Friday 6 November (5 nights)
• Monday 9 and Tuesday 10 November (2 nights)
• Monday 16 and Tuesday 17 November (2 nights)
Westbound closures will run from Roger Millward Roundabout to Commercial Road, including the Queen Street entry slip road. Eastbound closures will run from Daltry Street to Ferensway.
Please note city centre diversion routes will be in place for these closures. Please plan ahead, allow extra time, and follow signed diversion routes.
We’re sorry for any disruption and thank you for your patience while we complete this important work.
Work at Murdoch’s Connection footbridge
The closure will also allow for combined works at Murdoch’s Connection bridge for maintenance and repairs.
This will require closure of the bridge to pedestrians and cyclists - with diversion routes in place to the alternate crossing points on the A63 Castle Street including High St underpass.
Footpath closures eastbound and westbound adjacent to the A63 –
Monday 2 to Friday 6 November, 8pm to 6am (5 nights)
Monday 9 and Tuesday 10 November, 8pm to 6am (2 nights)
The footbridge will be closed –
Monday 16, Tuesday 17 November - 8pm - 6am (2 nights)
During this period, clearly signposted pedestrian diversion routes will be in place to maintain access to the surrounding areas.
These works will involve addressing identified defects on the structure as part of our ongoing commitment to maintaining the network.
By coordinating these activities and working collaboratively we aim to complete the necessary works efficiently, reducing the need for additional closures and minimising future disruption to members of the public. Further repair works are scheduled to resume in February 2027, with every effort being made to maintain safe public accessibility throughout the process.
If you have any further queries or concerns, please don’t hesitate to contact National Highways – email: [email protected] or telephone via the customer contact centre on 0300 123 5000.