GIBBSBORO CONSTRUCTION ACTIVITY
WEEK OF NOVEMBER 2
CAMDEN COUNTY ROAD INTERUPTIONS:
Monday November 2 & Wednesday November 4 – Permit # 26-07602
• Clementon Road East – 7:00 a.m. to 4:00 p.m. Think Pavers will continue performing a sewer tie-in. There will be a full road closure between Foster Avenue & Lakeview Drive North.
WORK AROUND SILVER LAKE:
• On Friday, October 30, the Sherwin-Williams team completed improvements to the outfall of a stormwater conveyance line that runs from East Clementon Road through 20 East Clementon Road and into Silver Lake. (See pictures) The path around the lake behind 20 East Clementon Road is reopened.
The public is reminded that Silver Lake is privately-owned and swimming, fishing, boating and other lake activities are prohibited.
The sidewalk along the southeast side of Clementon Road from Foster Avenue to the Lucas Homestead remains closed for reconstruction of the sidewalk/streetscape along the roadway. The sidewalk from Haddon Avenue to Wawa on the north (townhome) side of Clementon Road has been completed and is now open.
Curbing and utilities for the 6 East Clementon parking lot between the Lucas Homestead and Foster Avenue has been installed. Base coat paving is expected in about two weeks.
SCHEDULED SUPERFUND ACTIVITY:
• The Sherwin-Williams project team will continue collecting pre-design soil samples in the Hilliards Creek corridor this week and will do so over the next several months.
• Sherwin-Williams will be operating the interim Soil V***r Extraction (SVE) system on 1 Foster Avenue through November 10.
• Sevenson continues to dismantle the soil management pad located on 2/4 Foster Avenue and is completing final restoration and landscaping on the 2 and 4 Foster Avenue parking lot.
The project schedule may vary depending on weather conditions.