10/19/2026
🚧 Denbigh Interchange: Construction Starts Now 🚧
The I-64/Denbigh Boulevard Interchange (Phase I) is no longer just a plan. VDOT gave City Council its latest update, and crews are mobilizing this fall. Here’s what’s coming over the next six months so you can plan ahead:
📍 Oct–Nov 2026
• Crews and equipment arrive on site
• Lane shift and traffic control on I-64 West
• Construction of the I-64 West auxiliary lane begins
• Access between Richneck Rd and Denbigh Blvd will close permanently
• Utility work starts near the ramps
📍 Dec 2026–Jan 2027
• Widening begins on Denbigh Blvd near I-64
• New access built between St. Andrews Lane and Word Works Worship Center
📍 Feb–Mar 2027
• The I-64 lane shift comes down
• Short-term lane closures on Denbigh Blvd to remove the raised median
• Church access work is completed
📍 Warwick Blvd & Jefferson Ave intersections
Right-of-way acquisition runs from fall 2026 through summer 2027. Construction at these two intersections starts in Summer 2027. VDOT does not expect long-term lane closures there.
This is a $74.1M investment. It’s the first of two projects that together will deliver a full diamond interchange at Denbigh, with completion expected in Summer 2029. It means better access, safer travel, and real infrastructure for Uptown.
👉🏾 What you can do:
✔️ Leave extra travel time near Denbigh and I-64
✔️ Find a new route if you use the Richneck Rd connection
✔️ Share this post with your neighbors, your church family, and local businesses