09/22/2026
The Micro-Surfacing Project is scheduled to begin on 9/23/2026. Per the Contractor, they will start work in the 165th Street E, 167th Street E, and 169th Street E project areas. The project includes 165th Street E, 167th Street E, 169th Street E, Jennifer Lane, 180th Street E, Cleary Lake Court, Kane Avenue, Century Court, Century Lane, Harvest Hills Drive, Bonita Lane, Oak Hill Circle, Oak Hill Lane, Valley View Court, Woodridge Drive, Park Lawn Court, Gensmer Circle, Lucerne Trail, and Rolling Oaks Court. The work will take approximately 3-4 favorable weather days to complete and only minor delays are expected during construction. The roads will remain open to traffic and the new surface can be driven on within 10-20 minutes of application, depending on weather conditions. One lane will remain open to traffic at all times, please pay attention to the construction workers for instructions on driving through the work zones.