20/04/2026
New Project Update: Construction (Completion) of Multi-Purpose Building Including Related Facilities Central E/S, Balilihan, Bohol
Installation of Reinforcement For SOG and Roof Beam including Plumbing and Electrical Works.
20/04/2026
New Project Update: Construction of School Building
Balilihan Central Elementary School, Balilihan, Bohol
Final preparation for SOG Pouring (Plumbing works and Installation of concrete spacers)
20/04/2026
Project Update: PRO8 Admin Extension Building
Camp Sec. Ruperto K. Kangleon, Palo, Leyte
Ongoing construction activities continue across the site. Ground floor works include ceiling installation, door jamb installation, steel door fabrication, and ramp and canopy construction.
On the second floor, sanitary and electrical wiring works are currently in progress. At the roof deck, the team is working on the parapet wall and C-purlin installation.
Concrete mouldings are also ongoing throughout all floors. Stay tuned for more updates!
20/04/2026
New Project Update: Renovation of Balangiga MPS Old Building
Balangiga, Eastern Samar
Renovation works are currently ongoing, with key activities focused on improving and preparing the facility for further construction. This includes the fabrication of trusses, hauling of debris from demolition works, and removal of existing floor tiles.
These activities are being carried out to ensure proper site preparation and smooth progression of the renovation works.
20/04/2026
Site Update: Construction of Standard Type "B/C" Jiabong MPS Building
Ongoing works at the site include installation of reinforcement bars and formworks for stairs and upper roof beams. CHB piling and plastering works are currently in progress on the 2nd floor.
At the lower ground floor, preparation for skim coat application is also underway as part of the finishing works.
20/03/2026
Site Update: Construction of Standard Type "B/C" Jiabong MPS Building.
Construction continues to move forward smoothly!
On the ground floor, electrical wiring works are in progress, and stair formworks are being set up. The second floor is seeing active masonry works, including CHB piling and plastering. Up on the roof deck, trusses are being fabricated, and CHB piling is underway for the parapet walls.
Step by step, the building is taking shape—exciting progress all around! 💪✨
20/03/2026
Site update: PRO8 Admin Extension Building
Location: Camp Sec Ruperto K. Kangleon, Palo, Leyte
Construction is steadily moving forward!
Reinforcement bars and formworks are being installed for the third-floor columns. On the upper ground floor, CHB piling and plastering are in progress, while the lower ground floor is seeing ceiling framing and Ficem board installation.
The building is taking shape day by day, bringing us closer to completion! ✨🙏
20/03/2026
March 17, 2026 brought us together for a meaningful evening of welcoming new faces and bidding goodbye to those moving forward.
It was a night filled with joy, gratitude, and memories we’ll hold onto wherever life takes us.
Thank you, and best wishes on your exciting new journey ahead! ✨
28/02/2026
Construction Update | PRO8 Admin Extension Building
Construction of the PRO8 Admin Extension Building at Camp Sec. Ruperto K. Kangleon, Palo, Leyte is progressing steadily.
Work is currently focused on the installation of reinforcements and formworks for the columns from the second to the third floor, as well as masonry works at the lower ground floor, including CHB piling and plastering. These efforts are ensuring the building’s durability and quality as the project moves forward.
We look forward to the successful completion of the building and its future use by the community.✨🤞
28/02/2026
Construction Update | Brgy. Ubujan Multi-Purpose Building
Progress continues on the Multi-Purpose Building in Brgy. Ubujan, Tagbilaran City as we move closer to completion.
Application of silver finish aluminum paint to the C-purlins and angle bars is currently in progress, enhancing structural protection and ensuring a durable, quality finish as the project nears completion.
We look forward to turning this facility over to the community soon.✨🤞