10/28/2026
Wilson Downtown Construction Updates đźš§
Work to be completed the week ending 10/30/2026:
- Begin paving roadway sections between existing saw cuts and newly placed curb and gutter where areas are ready for paving.
- Paving will likely begin at the far west end near Stagecoach.
- No changes to traffic control are anticipated. However, flaggers may be used to assist trucks entering and exiting the construction area, resulting in minor impacts to the public.
- Continue placing concrete curb and gutter near the new west Hungry Jacks approach and Edmiston Spring.
- Complete final preparation for the new Hungry Jacks approach.
- Reopen the Post Office approach in its entirety, pending satisfactory concrete break results.
- Switch traffic to the new west Hungry Jacks approach and close the existing middle approach, pending satisfactory concrete break results.