11/04/2026
WEEK 23 (NOV 2)
Monday, Jeremy & Dawson Roberson with Ridgeline Contracting came to do the excavation work on the private access road and upper parking/turn around. They evened and widened out where needed and then laid gravel. The Lodge’s skid steer was put to work too with its new bucket attachment. This will really help this winter when we snow blow around the sides and back of the lodge.
They will return in the spring to remove the large pile of asphalt shavings in the parking lot and the large pile of stones and concrete cuts west of the lodge. These two piles have been here since 2019 and it will be great to have them gone.